Lining of two parking decks at Saveways Crescent Centre

BKV Holdings was contracted by Peet’s Roofing to line two parking decks at Saveways Crescent Centre.

The one 1 762m² roof was lined with a CIN EP 500 system and the other 1 513m² structure with an epoxy-fairing coat. BKV Holdings accelerated the project by completing the blasting and cleaning components in under a week to finalise the entire project in less than 30 days as requested by the client.

Our state-of-the-art solution deployed at Parking Deck 1 entailed:

  • Track blasting to obtain a surface profile;
  • Applying a CIN C floor primer; and
  • Applying a CIN EP 500 polyurea.

Our state-of-the-art solution deployed at Parking Deck 2 entailed:

  • Track blasting to obtain a surface profile; and
  • Applying an epoxy fairing coat;

We used the following equipment on this project:

  • A track-blasting machine;
  • An EXP11 spray machine;
  • A Festo mixer; and
  • A water bowser.